ReportTransportation
Front Street Bridge will close for 14 months starting Jan. 11
City Council approved an $18.6 million rebuild Monday night. Drivers will detour over the Mill Street crossing, and the Tuesday farmers market is moving to Depot Square.
Correction, Nov. 10 An earlier version of this story gave the wrong start date for the closure. Work begins Jan. 11, not Jan. 4.
The Front Street Bridge, which carries about 14,000 vehicles a day across the Lantern River, will close to all traffic for 14 months beginning Jan. 11 so crews can replace its deck and steel bearings.
The Lantern City Council voted 6–1 on Monday night to award the $18.6 million contract to Columbia Span Builders of Salem. A state bridge grant covers $11.2 million. The rest comes from the city’s transportation fund and a 2024 road bond.
Councilor Anita Hale cast the only no vote. She asked whether the work could be done one lane at a time. Public Works Director Carl Jensen said that would stretch the job past two years and add about $3 million.
Traffic on the bridge has not returned to where it was before 2020. City counts show weekday traffic fell by a fifth that spring and has settled about 12% below the 2016 level.
Weekday vehicles on the Front Street Bridge
2016–2026Average weekday count, both directions, from the city’s permanent counter at the west abutment. 2026 runs January to October.
The detour
Drivers will be routed over the Mill Street crossing, a mile upstream. City traffic engineers expect the detour to add about six minutes at morning and evening rush hour. New signals at Mill and 3rd go live Dec. 14.
“We looked at keeping one lane open. It adds a year of construction and a year of people living next to it.”
People on foot and on bikes will use a temporary walkway on the bridge’s north side through most of the project. The walkway will close for about three weeks in early summer while the deck is poured.
Buses and the Tuesday market
Lantern Transit’s Route 4 will stop at Depot Square instead of Front and 2nd. The agency is adding two buses so the route can keep running every 20 minutes.
The Tuesday farmers market, which has filled the 100 block of Front Street since 1987, will move to Depot Square for the 2027 season. Market manager Lucia Ferreira said all 46 vendors have been offered a stall.
What happens next
Crews will begin moving utility lines in December. The city will mail a detour map to every address in the 97399 ZIP code before the holidays and hold an open house at the Lantern Community Center on Dec. 3 from 5 to 7 p.m.
Who pays for the $18.6 million rebuild
| Source | Amount | Share |
|---|---|---|
| State bridge grant | $11.2 million | 60% |
| City transportation fund | $4.9 million | 26% |
| 2024 road bond | $2.5 million | 14% |
| Total | $18.6 million | 100% |
Source: City of Lantern, council agenda item 7B, Nov 9, 2026
Key dates
- Dec. 3Open house, Community Center, 5–7 p.m.
- Dec. 14New signals at Mill & 3rd turn on
- Jan. 11Bridge closes to all traffic
- Early summerWalkway closes about 3 weeks for the deck pour
- March 2028Planned reopening